Many project gaps sit between two suppliers. One team expects a cable, another expects a configured interface, and neither has priced the work. A simple responsibility schedule makes those assumptions visible early.
Follow a signal from field to display
Take one representative measurement and trace its path through the instrument, wiring, panel, controller and supervisory screen. At each handover, identify who supplies, installs, configures and checks the relevant work. Repeat this for a command path where applicable.
Include work supplied by the owner
Existing drawings, access permissions, site facilities and operational coordination may sit with the client. Record these dependencies alongside supplier work. Avoid treating them as background tasks that will somehow be ready when commissioning begins.
Assign approval as well as delivery
The person producing a drawing may not be the person authorised to approve it. Identify the review route and who accepts each completed interface. Use clear descriptions instead of a broad line saying “all integration by others”.
Resolve overlaps before ordering
Discuss any duplicated or unassigned work while proposals can still be clarified. The PLC procurement planning guide shows how the responsibility schedule supports a comparable quotation.
Frequently asked questions
Why trace a representative signal across a PLC project?
It exposes the handovers between field devices, panels and software where delivery or verification responsibilities can be missed.
Should the owner’s tasks appear in the responsibility schedule?
Yes. Site access, existing information and operational coordination can be dependencies just as important as supplier deliverables.
Does supplying a component automatically mean approving its integration?
Keep delivery, configuration, checking and approval responsibilities explicit; they may belong to different parties.